Shore Protection Project at Fainu well underway

Maldives Transport and Contracting Company (MTCC) has said that a large portion of the Raa Atoll Fainu Shore Protection Project has been completed.

Taking to Twitter today, MTCC said that an overall 63 percent of the project has been completed and the revetment phase for the shore protection was commenced on 1 November 2021.

The project was mobilized on 14 September 2021 and entails 8,100 cubic meters of soil backfill and 250 meters of geo-bag revetment.

The Shore Protection Project was contracted to the MTCC for MVR 8.96 million.