Angolhitheem harbor project moving rapidly

Maldives Transport and Contracting Company MTCC has prepared for the installation of pre-cast blocks for the quay wall as part of the Raa Atoll Angolhitheem Harbor Development Project.

Presenting an update on the ongoing project on Twitter today, MTCC said that the pre-cast blocks were delivered on 1 April delivered and the installation is set to begin within the month.

The Angolhitheem Harbor Development Project entails 42,615 cubic meters of harbor dredging, 221 meters of outer sea wall, 166 meters of revetment 1,110 square meters of pavement along with the installation of the harbor and port lights.