Harbor development project at Alifu Dhaalu Hangnameedhoo has been mobilized.
The project was contracted to the Maldives Transport and Contracting Company (MTCC) for MVR 32.2 million in December 2019. MTCC said that the project site was mobilized on Friday to start the project.
The project entails a harbor of 6.363.1 cubic meters, 204 meters of outer sea wall, 160 meters of revetment, 226 meters of inner sea wall, a pavement of 1,330 square meters and street lamps.