Maldives Transport and Contracting Company (MTCC) has mobilised B. Eydhafushi Harbour Development Project site, R. Hulhudhuffaaru Shore Protection Project site, and N. Kendhikulhudhoo Harbour Upgrade and Boat Beaching Area Project site.
Scope of work for B. Eydhafushi project includes 28,304cbm maintenance dredging operations, 3,354cbm channel dredging operations, 402m quay wall, 170m breakwater, 383m revetment, 11m x 11m ramp, 18m x 2m bridge, 1,814sqm pavement, installation of harbour lights and mooring buoys.
The project is valued at MVR 64.67 million.
Scope of work for R. Hulhudhuffaaru project includes 473m groyne, 320m revetment, 100m low crested breakwater, and 20,500cbm beach nourishment.
The project is valued at MVR 29.94 million.
Scope of work for N. Kendhikulhudhoo project site includes 28,393cbm new harbour basin dredging operations, 30,480cbm maintenance dredging operations, 12,968cbm channel dredging operations, 12,038cbm boat beaching area basin dredging operations, 14,220cbm boat beaching area channel dredging operations, 249m quay wall, 368m breakwater, 130m revetment, 246m groyne, 11m x 11m ramp, 86m x 1.5m jetty, 1,990sqm pavement, installation of harbour lights and navigational lights, and installation of mooring buoys.
The project is valued at MVR 73.16 million.