Maldives Transport and Contracting Company (MTCC) has revealed that the work on design and build of Sh. Bilehfahi Harbor Development Project is well underway, with overall 79% project progress.
They noted that they have completed breakwater profiling works.
The scope of the project includes, dredging operations of 50,376cbm, construction of a 181m quay wall, a 170m revetment, a 434m breakwater, installation of 1565sqm pavement, installation of navigation lights and streetlights.
The value of the project is MVR 28.42 million.