Maldives Transport and Contracting Company (MTCC) has revealed that work on Design and Build of Dh. Hulhudheli Harbor is well underway, with overall 85% project progress.
They further added that the street lights required for the harbor has been delivered to the project site.
Scope of works for the project include dredging and excavation operations of 49,612 cbm; the construction of a 432m quay wall; a 337m breakwater; and a 252m revetment. Additionally, the installation of 1,645sqm of paved area and streetlights will also be undertaken.
The value of the project is MVR 45.8 million.