Maldives Transport and Contracting Company (MTCC) has revealed that the third shipment of precast concrete blocks required for quay wall construction for Dh. Meedhoo Harbor Development Project have been delivered to the project site.
Installation of precast concrete blocks is ongoing, with 57% completion.
Scope of the project includes, dredging and excavation operations, construction of a 373m breakwater; a 35m revetment; a 294m quay wall; a 11m x 11m ramp; installation of 1,470 sqm pavement; navigational lights and harbor lights.
The value of the project is MVR 34.07 million.