Maldives Trading and Contracting Company (MTCC) has revealed that work on design and build of Hdh. Hanimaadhoo Harbor Development Project is well underway, with overall 65% project progress.
According to the company, quay wall concrete works are ongoing, with 98% completion.
The Hdh. Hanimaadhoo Harbour project consists of; new harbor basin dredging of 53,522.50cbm; harbor entrance channel dredging of 31,575.50cbm; construction of a 355m breakwater; a 50m revetment; a 270m quay wall and installation of 2,583sqm of paved area.
The value of the project is MVR 64.6 million.