Maldives Transport and Contracting Company (MTCC) has revealed that the irst shipment of rock boulders required for Lh. Felivaru Harbor development and Reclamation project have been delivered to the project site.
Dredging and Reclamation works are ongoing with 95% completion.
Scope of works for the project include, reclamation operations of 6 hectare; dredging operations of 229,663.36cbm; construction of a 220m quay wall; a 148m breakwater; a 270m revetment.
The value of the project is MVR 113.3 million.