According to Maldives Transport and Contracting Company (MTCC), the final shipment of concrete blocks required for the construction of quay wall of K. Hinmafushi Harbor have been delivered to the project site.
The quay wall concrete block installation works of the project is ongoing, with 81% completion.
The scope of the project includes, dredging and excavation operations of 28,760cbm; construction of a 38m breakwater; a 287m revetment; a 172m quay wall; installation of 772sqm harbor pavement; navigation lights and streetlights.
The value of the project is MVR 25.88 million.