Quay Wall on Hinnavaru South side completed

Maldives Transport and Contracting Company MTCC has said that the quay wall construction has been completed as part of the Lhaviyani Atoll Hinnavaru South Harbor Development Project.

Taking to Twitter this morning, MTCC said that while the quay wall on the south side has been completed, the quay wall of the northern side is underway with the installation of the concrete blocks in progress.

The project entails 3.2 hectares of land reclamation via dredging and rainbowing, a harbor of 65,170.76 cubic meters, 421 meters of inner sea wall, 123.9 meters of outer sea wall and 170.55 meters of revetment.

Housing Ministry contracted the project to MTCC for MVR 99.52 million.