MTCC

Miladhoo Harbor close to completion

Maldives Transport and Contracting Company (MTCC) has said that the harbor development project in Noonu Atoll Miladhoo is close to completion.

Taking to Twitter this morning, MTCC said that the project is well underway with 90 percent of the project completed and the final shipment of the rock boulders required for the project delivered to the site on Tuesday.

Miladhoo Harbor Development Project entails 37,222 cubic meters of dredging for depth, 258 meters of outer sea wall, 286 meters of inner sea wall, 137 meters of revetment, 1,430 square meters of pavement along with the installation of street lamps and port lights.

The project worth MVR 45.26 million was contracted to my MTCC by the Ministry of National Planning, Housing and Infrastructure in August 2019.