Landhoo Harbour project is well underway

Maldives Transport and Contracting Company (MTCC) has said that the Noonu Atoll Landhoo Harbour Development Project is well underway.

The company said that an overall 53 percent of the project has been completed and the dredging works for the new harbor basin project is currently ongoing, with 96 percent currently completion.

The project entails a 25,000 cubic meter harbor with 256 meters of inner sea wall, 401 meters of outer sea wall, 60 meters of revetment and 1,280 square meters of pavement along with harbor and port lights installation.

Landhoo Harbour Development Project was contracted to MTCC for MVR 35.60 million.