Ihavandhoo Harbor Development Project underway

Maldives Transport and Contracting Company (MTCC) has said that the Haa Alifu Atoll Ihavandhoo harbor development project is well underway with the dredging f the harbor basin close to completion.

The company was contracted he project in August 2019 for MVR 48.5 million to be completed within 400 days.

MTCC said that the project is well underway with 98 percent of the basin dredging phase of the project has been completed and the first shipment of materials for the inner sea wall concrete work have been delivered to the project site.

Ihavandhoo harbor development project entails 30,509 cubic meters of harbor dredging and land reclamation, 284 meters of outer sea wall, 95meters of inner sea wall, 178meters of revetment along with 4,582 square meters of pavement, street and harbor lights installation.