The Shaviyani Atoll Lhaimagu Harbor Development Project has been mobilized to start..
Maldives Transport and Contracting Company (MTCC) said that the project site was mobilized on Monday to start the project.
The project was contracted to MVR 53 million from the state budget to the MTCC on 10 December 2019.
Lhaimagu harbor project entails the development of a 31,000 cubic meter harbor, 350 meters of outer sea wall, 276 meters of inner sea wall, 500 meters of revetment, a pavement of 1,380 square meters along with the installation of street lamps.