MWSC awarded water and sewerage projects in 15 islands, water systems in 5 islands

Male’ Water and Sewerage Company (MWSC) has been contracted to establish water and sewerage systems in 15 residential islands and water systems in five additional islands.

From the National Planning, Housing Ministry, Director General Fathimath Shana Farooq signed on the contracts while Managing Director Hassan Shah signed on behalf of MWSC.

As per the planning ministry, the cumulative value of the contracts under the design and build rule is above MVR 1.31 billion. The payments are to be made over installments within four years.

The projects:

- A. A. Feridhoo water and sanitation project: MVR 69.33 million

- A. A. Himandhoo water and sanitation project: MVR 65.83 million

- B. Kamadhoo water and sanitation project: MVR 56.66 million

- B. Maalhos water and sanitation project: MVR 60.45 million

- H. A. Maarandhoo water and sanitation project: MVR 72.81 million

- H. A. Thakandhoo water and sanitation project: MVR 76.45 million

- H. A. Vashafaru water and sanitation project: MVR 78.92 million

- H. Dh. Hirimaradhoo water and sanitation project: MVR 69.14 million

- H. Dh. Kumundhoo water and sanitation project: MVR 102.17 million

- Sh. Goidhoo water and sanitation project: MVR 86.05 million

- N. Maafaru water and sanitation project: MVR 94.42 million

- N. Fodhdhoo water and sanitation project: MVR 58.15 million

- R. Fainu water and sanitation project: MVR 63.34 million

- Lh. Olhuvelifushi water and sanitation project: MVR 80.08 million

- A. Dh. Kunburudhoo water and sanitation project: MVR 45.12 million

- A. A. Mathiveri water project: MVR 38.83 million

- H. A. Muraidhoo water project: MVR 46.85 million

- Sh. Feevah water project: MVR 49.60 million

- N. Henbadhoo water project: MVR 41.36 million

- R. Innamaadhoo water project: MVR 50.77 million

- The projects were contracted to MWSC under build and design method.

According to the Planning Ministry, MWSC is required to complete the water and sewerage projects in 18 months and the water projects in 15 months.