Maldives Transport and Contracting Company (MTCC) has said N. Manadhoo Harbour Channel Dredging and Breakwater Construction Project is currently underway with 50% project completion.

MTCC said the ramp construction work has begun and jetty column installation has reached 52% completion. Dredging of existing harbour is currently ongoing at the site with 30% progress.

Scope of works for the project include dredging and excavation operations of 29,038cbm, construction of a 195m breakwater, a 188m revetment, a concrete bridge, a ramp, and installation of navigational aids.

The project is valued at MVR 30.3 million.