GDh. Thinadhoo water drainage system has been installed successfully.

The project's testing and commissioning was completed on 12-13 May 2023.

The project was awarded to Senock Trade Combine Pvt Ltd on 13 October 2019. The project is valued at MVR 16.8 million.

The project was agreed to be completed within a year, but Environment Ministry stated that delays occurred due to Covid-19 pandemic. Additional changes to the designs also caused delays in the project, the Ministry added.

Environment Ministry stated that the project has been completed and will provide great convenience to the people of GDh. Thinadhoo.