Maldives Water and Sewerage Company (MWSC) has revealed that a significant amount of work for the Mathiveri Water System Project has been completed.

A message shared by the company with the media today noted that under the project, they have completed laying the 6.7km pipeline and drilling of the bore holes as required.

In addition to this, the placement of two water tanks and connecting water to individual households has also been completed along with the construction of the facility building to house the water plant.

MWSC further highlighted that works on placing two RO Water Plants are also proceeding, adding that the required materials for water analysis will also be provided under the project.