Maldives Transport and Contracting Company (MTCC) has said that Th. Gaadhiffushi Water Supply & Sewerage Project is well underway with 91% overall project progress.

MTCC said the water network works are currently ongoing with 85% completion.

Scope of work for the project include construction of an administrative building, RO plant installation, 4,070m sewerage network, water network; brine and sewer outfall, a 210m pumping main and outfall and installation of 2 pump stations.

The project is valued at MVR 20.9 million.