Maldives Transport and Contracting Company (MTCC) has revealed that the third shipment of rock boulders required for the Seenu Atoll Hulhudhoo Harbor Development Project have been delivered to the site.

MTCC revealed that the construction of the revetment is ongoing, with 94% completion.

Scope of works includes 88,623cbm of new harbor basin dredging operations, construction of a 742m quay wall, a 50m breakwater, a 25m groyne, installation of harbor pavement, construction of a bridge, a ramp, and installation of harbor lights.

The value of the project is MVR 66.3 million.