Maldives Transport and Contracting Company (MTCC) has revealed that the quay wall concrete works and harbor basin dredging operations for Dh. Meedhoo Harbor Development Project are currently ongoing, with 78% and 73% completion respectively.

Scope of the project includes, dredging and excavation operations, construction of a 373m breakwater; a 35m revetment; a 294m quay wall; a 11m x 11m ramp; installation of 1,470 sqm pavement; navigational lights and harbor lights.

The value of the project is MVR 34.07 million.