Maldives Transport and Contracting Company (MTCC) has revealed that the Sh. Feydhoo quay wall block installation work has been completed on 21st August 2022.

They further added that the scope of the project includes, dredging operations of 27,500cbm, construction of a 276m quay wall, a 90m revetment, a 378m breakwater, installation of 1380sqm harbor pavement, installation of navigation lights and streetlights.

The value of the project is MVR 35.6 million.