Maldives Transport and Contracting Company (MTCC) has said full shipment of precast concrete blocks required for quay wall construction of Sh. Feydhoo Harbor has been delivered to the project site.

MTCC said preparations to commence quay wall construction works are in motion.

The scope of works for the project includes dredging operations of 27,500cbm, construction of a 276m quay wall, a 90m revetment, a 378m breakwater, installation of 1380sqm harbor pavement, installation of navigation lights and streetlights.

The project is valued at MVR 35.6 million.